Kitchener Project: CIPP Lining of 900mm Stormwater Pipe
Project Details:
Client: Heb Construction Limited
Commenced: January 2022
Completed: February 2022
Project Manager: Paul Norris
Main Contractor: New Zealand Lining Limited
Value: $40,000
The client needed to rehabilitate the existing 900mm diameter stormwater located in a very environmentally sensitive location (Milford, Auckland).
Project Scope:
The project involved the supply and installation of a CIPP liner of 900mm diameter stormwater pipe across Kitchener Road. The above pipe discharges the stormwater into Wairau Creek close to the Milford Marina.
Project Outcome:
+ All construction work was completed to the required specifications. Samples from the CIPP installation were taken for testing. The mechanical properties of the samples exceed the standard results for strength and flexure modules.
+ Our safety, environmental performance, work quality, and public and client communications exceeded the performance targets through the implementation of our procedures and control measures. No environmental or safety incidents were recorded.
+ The quality of the final product met the client’s expectations.